Saluran Reklamasi Tambang
Case Study Information

Project Type: Channel Lining
Project Type (Other): Mining

Project Start Date: August 9, 2025

Project Objective:
The objective of this project is to protect the existing channel from surface erosion around the channel. Immediate action is required due to concerns that the existing soil will further loosen and cause surface erosion during the rainy season.

Project Location: Batu Sopang District, Paser Regency, East Kalimantan

Contractor: In-House Contractor
Number of Installers: 8

Client/Project Owner: Gold Mining Company in East Kalimantan Province

Amount of Concrete Canvas Used: 14,250 m²

Roll Format: Bulk Roll

Type/Thickness: CCX-M

Layup Method: Transverse

Equipment used

  • Excavator
  • Spreader Bars
  • Water Truck
  • Cutter/utility knife
  • J-Pin 40 cm
  • 30 mm stainless steel screws

Alternatives and Reasons for Choosing Concrete Canvas

Before Concrete Canvas, channels were constructed using used tires. However, in addition to being time-consuming to install, this material had a short lifespan and required regular maintenance to ensure the anchors were securely installed to prevent erosion during high water flows. Concrete Canvas became the solution because it was easier, faster, and more durable than previous materials.

Environmental Conditions

The project is being implemented in several reclamation areas where weather conditions can change rapidly. This requires solutions that are quickly implemented and able to withstand sudden environmental changes.

Land Preparation

  • Vegetation clearing
  • Land contour re-leveling and channel profile re-shaping

Installation, Bonding, and Sealing Methods

The Concrete Canvas CCX-M is installed transversely with overlapping joints aligned with the water flow. Fastening is done using 30 mm stainless steel screws spaced 10 cm apart on each overlap. Additionally, 40 cm long J-Pins are installed at each connection on the channel shoulder to ensure stability and ensure the Concrete Canvas adheres perfectly to the soil substrate.

Hydration Method

The hydration process is carried out using a hose connected to a water pump, with the water source coming from a nearby pond around the project site.

Installation Duration

Installation productivity reaches around 400-500 m² of Concrete Canvas per day.

Project Success

The project was deemed a success. The client was satisfied and plans to reorder annually for installation throughout the reclamation area.